Actions
Task #16
open
PK
PK
[QA-01] End-to-end smoke test across every module above, all 3 personas (customer/seller/admin), with particular attention to the security fixes (SEC-01/02/03) actually blocking what they're supposed to block.
Task #16:
[QA-01] End-to-end smoke test across every module above, all 3 personas (customer/seller/admin), with particular attention to the security fixes (SEC-01/02/03) actually blocking what they're supposed to block.
Start date:
10 Aug 2026
Due date:
% Done:
0%
Estimated time:
Description
Module: Whole App
Task:
End-to-end smoke test across every module above, all 3 personas (customer/seller/admin), with particular attention to the security fixes (SEC-01/02/03) actually blocking what they're supposed to block.
Why It Matters:
A security fix that silently breaks checkout is worse than the vulnerability — verify, don't assume.
Target Week: Week 3
Excel Owner: Whole team
Excel Priority: P0 - Critical
Excel Status: Not Started
Sprint Plan ID: QA-01
No data to display
Actions